The Bold Voice of J&K

Power shutdown in Jammu

0 45

power-cut-e1371137910898 STATE TIMES NEWS
JAMMU: To carry out the work of PCC pole erection and installation of HT/LT cable by M/s IRCON International Ltd under RAPDRP project, the power supply to Prem Nagar, Christian Colony, Upper Gummat and Lower Gummat shall remain affected on 12th July from 7:00 to 10:00 AM.
Meanwhile, to carry out the work of dismantling of 25 KVA HVDS on C-18, C-22 and D-4 feeders by M/s IRCON, the power supply to Canal Road, Shakti Nagar, Krishna Nagar, Dogra Mohalla, Lajpat Nagar, Patel Nagar, CID Office, Guest House, Mohinder Nagar, Ambphalla, New Manda Sub-Station, Manda Wild Life Sanctuary, Ustad Mohalla shall remain affected on July 12, 14, 16, 18 and 19 from 8:00 to 11:00 AM (Alternate dates).

Leave a comment
WP Twitter Auto Publish Powered By : XYZScripts.com