Power shutdown in Jammu

0 51

STATE TIMES NEWS
JAMMU: To carry out the works by M/S IRCON under R-APDRP works, 11KV feeder CH-5 emanating from 33/11 KVA Receiving station Channi Himmat, the power supply to Channi Rama, Malik Market, Pamposh Colony, Chinar Colony and its adjoining areas shall remain under shut down on 6th March from 10:00 AM to 2:00 PM.
Meanwhile in order to carry out the works of excavation of foundation for erection of 13 Mtr. Long ST Pole for stringing of conducter for 33 KV Line and clear the corridor of 33 KV Line, 11 KV bare conductors are proposed to be replaced by H.T AB Cable etc by M/S IRCON under R-APDRP, 11 KV Feeder Ansal emanating from 10 MVA Receiving station Ratnuchak, Birpur, the power supply to Ansal, Ratnuchak, Birpur and its adjoining areas shall remain affected on March 05, 06, 08 and 09 from 9:00 AM to 2:00 PM. The shutdown is subject to fair weather conditions.