Power shutdown in Jammu

 STATE TIMES NEWS
JAMMU: To carry out work of charging of 10 MVA, 132/11 KV Sub-Station through 132 KV newly laid Transmission Line from CSTL for Chenani-Nashri Tunnel project by M/s IL and FS Transportation Networks Limited, the shutdown of 132 KV D/C CSTL is allowed on 2nd October from 7:00 AM to 12:00 Noon.
During the shutdown, the power supply shall not be affected as Batote and Chanderkote Grid Stations shall be fed from 220 KV Grid Station Ramban.