JAMMU: To carry out the development works by M/s IRCON International Ltd. under R-APDRP project, the power supply to Sidhra and PHE installations fed from Janipur-Sheetli line shall remain affected on March 23, 25, 27 and 29 from10:00 AM to 2:00 PM.
Similarly, the power supply to Lower Roop Nagar, Housing Colony, Chinor, Durga Nagar, Buta Nagar and adjoining areas fed from Janipur-Roop Nagar line (BH-1) shall remain affected on March 24, 26 and 28 from 10:00 AM to 2:00 PM.
Meanwhile, to carry out work the upgradation works by M/s IRCON International Ltd. under R-APDRP scheme, the power supply to Karan Nagar, Gujjar Nagar, Panjthirthi, Jain Bazar, Ustad Mohalla, Kachi Chawni, Jullaka Mohalla, Boriawala Pump House and adjoining areas fed from 33 KV G-5 and G-8 lines emanating from Grid Station Gladni shall remain affected on March 23from 6:00 AM to 8:00 AM.
However, to carry out stringing of Panther Conductor of 33 KV new G-6 line between Grid Station Gladni and 33 KV Receiving Station Channi Himmat, the power supply to Channi Himmat, Malik Market, Police Quarters, Sainik Colony, Chowadi and its adjoining areas fed from 33 KV line emanating from 220/132/33 KV Grid Station Gladni shall remain affected on March 23, 25 and 27 from 10:00 AM to 2:00 PM.

Leave a comment
WP Twitter Auto Publish Powered By : XYZScripts.com