JAMMU: To carry out stringing work between location no. 25/0 and 26/0 at village Laliyana, the power supply to Arnia, Alha, Suhagpur, Treva, Chak Shera, KotliJabowal, Makhanpur & Rathana and their adjoining areas and Ramgarh, Nandpur, Jerda, Baba Chambyal, Adhlehar-I, BSF, Rangoor, Kamore and Barote and their adjoining areas fed from Suhagpur and Nandpur feeders shall remain affected on 20th April from 10:00 AM to 05:00 PM.
Meanwhile, In order to carry out upgraded reconductoring of 33 KV OH line by M/s IRCON International Ltd, the power supply to Seora, Babliyana, Jeevan Nagar, Digiana Ashram, Raina Colony, Air Force, MES, Apna Vihar & parts of Kunjwani fed from 33/11 KV Sub-Station (GG-3 line) shall remain affected on April 18, 20, 22, 24, 26, 28 and May 02, 04, 06, 08, 10, 12, 14, 16 and 18 from 9:00 AM to 1:00 PM.
Similarly, to carry out erection of line isolator and its jumpering, the power supply to Gandhi Nagar, Rail Head, Bahu Plaza, Parts of Trikuta Nagar and RBI fed from 33/11 KV Sub-Station JDA Complex (G-2 line) shall remain affected on 20th April from 8:00 AM to 1:00 PM.
Meanwhile, to carry out interconnection of new 11 KV incomer cable and shifting of load on new power transformer, the power supply to Trikuta Nagar and its adjoining areas fed from 33/11 KV Sub Station Trikuta Nagar shall remain affected on 21st April from 8:00 AM to 11:00 AM.
Similarly, to carry out shifting of existing VCB-CT, the power supply to Gandhi Nagar, Rail Head, Bahu Plaza, Parts of Trikuta Nagar and RBI fed from 33/11 KV Sub-Station JDA Complex (G-2 line) shall remain affected on 22nd April from 8:00 AM to 12:00 Noon.
Meanwhile, to carry out putting load on new transformer and shifting of load on new power transformer, the power supply to Channi Himmat, Sainik Colony, MES Sunjwan, Chowadi, Malik Market and its adjoining areas fed from 33/11 KV Sub Station Channi Himmat shall remain affected onApril 23 from 08 am to 01 pm.
Similarly, to carry out jumpering of additional bay work, the power supply to Gandhi Nagar, Rail Head, Bahu Plaza, Parts of Trikuta Nagar and RBI fed from 33/11 KV Sub-Station JDA Complex shall remain affected on 24th April from 8:00 AM to 12:00 Noon.
Meanwhile, to carry out interconnection of new 11 KV incomer cable, the power supply to Sainik Colony, Chowadi and its adjoining areas fed from 33/11 KV Sub-Station Sainik Colony shall remain affected on 25th April from 8:00 AM to 1:00 PM.